By Sheldeen Joy Talavera, Reporter
THE PHILIPPINES is still on track to meet its renewable energy (RE) targets despite the surrender of contracts covering several gigawatts (GW) of capacity, the Department of Energy (DoE) said, noting that the move could open opportunities for other developers.
Energy Secretary Sharon S. Garin said the relinquishment of contracts was a voluntary decision made by developers after determining that their projects were no longer viable, and was not a result of government intervention.
“This is the move, the direction that the DoE is going for that we want serious developers getting our contracts,” she said at a press briefing on Tuesday.
Ms. Garin said developers are responsible for assessing a project’s viability during the pre-development stage.
RE service contracts may end either through voluntary relinquishment by developers or termination by the DoE for failure to meet contractual obligations.
ACEN Corp., one of the country’s leading RE players, previously disclosed that it has voluntarily relinquished 12 wind and solar energy service contracts with a potential capacity of nearly 5 GW.
The Ayala-led company said the move was part of its strategic shift toward project execution, operational performance and capital efficiency, and was aligned with the DoE’s ongoing service contract cleanup initiative.
The cleanup drive, which began in 2024, aims to ensure that only serious developers hold RE service contracts and that awarded areas are pursued by companies capable of developing them.
“What we don’t want are those that are getting contracts without properly studying the projects — simply holding on to the contracts and selling them when an interested buyer comes along,” Ms. Garin said.
As of July 2025, the DoE had awarded around 1,400 RE service contracts with a combined potential capacity of 130 GW.
However, not all awarded projects have moved forward. Over the past two years, the agency recorded the termination or relinquishment of 163 service contracts representing nearly 18,000 megawatts of potential capacity.
The contract cancellations come as the Philippines seeks to expand the role of renewables in its power sector, targeting a 35% share in the generation mix by 2030 and 50% by 2040.
Energy Assistant Secretary Mandy B. Romero said the Philippines is still on track to hit these targets as other developers could pursue projects in areas vacated by companies that relinquished their service contracts.
“This isn’t a setback and it’s a part of the regulatory enforcement responsibilities of the Department of Energy to protect consumers,” she said.
Jose M. Layug, president of the Developers of Renewable Energy for AdvanceMent, Inc. and a former Energy undersecretary, said the government must balance efforts to weed out nonperforming developers with support for serious developers facing delays beyond their control.
“The DoE canceling nonmoving and noncompliant RE service contracts is a good signal that the DoE is firm in ensuring that RE projects are implemented,” Mr. Layug told BusinessWorld.
“At the same time, DoE needs to balance its clean-up efforts with helping out legitimate and serious contractors who face legitimate development struggles due to force majeure issues like delays in permits and registrations,” he added.
Mr. Layug said the country’s RE goals remain doable as long as the government is fully committed.